PLD 2018 Lah151
S. 173, Cr.PC-proviso [as added by Criminal Law
(Amendment) Act (XXV of 1992)]---Investigation---Interim report---Scope---Investigation
was to be completed without unnecessary delay and as soon as it was completed,
Officer-in-charge of the Police Station was required to submit challan through
Public prosecutor but not later than fourteen days---If the investigation was not
completed within a stipulated period of fourteen days from the date of recording of
FIR then Officer-in-charge of Police Station would submit an interim report within
three days of expiry of period of fourteen days stating therein the result of
investigation---Court on the basis of such interim report, would commence
trial.